Done once, done right. No ambiguity, no disputes on site - 30 storey tower, concrete construction, all suspended slabs left 3/8" shy of finished height with a rough Concrete Surface Profile (CSP) of 5 or 6 (note: an open rough surface profile also facilitates slab drying). Hydraulic Cement Underlayment (3/8" topping) planned and budgeted for well in advance, primed and poured 4 months later to build the slab up to finished height. 10' Straight Edge tests measured 1/16" over 10' (2mm over 3m) everywhere, even the most challenging test spots, such as up to support columns where slabs typically slop away, exceeded floor covering industry standards of 1/8" over 10' for a suspended slab. www.nfca.ca
|